Meeting Agenda
|
|---|
|
1. Open Meeting
|
|
2. Roll Call
|
|
3. Items of Business
|
|
3.A. Consider the Agreement Between City of Crete and JEO Consulting Group, Inc. for Professional Services Crete Water Main Project No: 231835.00
|
|
3.B. Consider the Preliminary Engineering Services Agreement Between the City of Crete and JEO Consulting Group, Inc. Project No. DPS-76(53) Control No. 13631 Crete Pedestrian Bridge Project
|
|
3.C. Amend Caselle Master Agreement
|
|
3.D. Consider the Contractor's Pay Estimate No 3 Application for Payment From JEO Consulting Group, Inc for NLC, LLC for the 2024 Crete Street and Alley Improvements Engineer's Project No: 240578.00 in the amount of $474,008.61
|
|
3.E. Discuss online payments with Caselle
|
|
4. Officers' Reports
|
|
5. Adjournment
|
|
Agenda Item Details
Reload Your Meeting
|
|||
|---|---|---|---|
| Meeting: | August 18, 2026 at 5:00 PM - Public Works Committee Meeting | ||
| Subject: |
1. Open Meeting
|
||
|
Rationale:
|
|||
| Subject: |
2. Roll Call
|
||
|
Rationale:
|
|||
| Subject: |
3. Items of Business
|
||
|
Rationale:
|
|||
| Subject: |
3.A. Consider the Agreement Between City of Crete and JEO Consulting Group, Inc. for Professional Services Crete Water Main Project No: 231835.00
|
||
|
Discussion:
City Administrator, Tom Ourada, discussed how USDA has approved the water remediation.
|
|||
|
Action(s):
|
|||
|
Attachments:
|
|||
| Subject: |
3.B. Consider the Preliminary Engineering Services Agreement Between the City of Crete and JEO Consulting Group, Inc. Project No. DPS-76(53) Control No. 13631 Crete Pedestrian Bridge Project
|
||
|
Discussion:
City Administrator, Tom Ourada, discussed how this is an engineering agreement between the City, JEO, and State to do the pedestrian crosswalk bridge in the Boswell area. This is how the City proceeds with feasibility and preliminary design.
|
|||
|
Action(s):
|
|||
| Subject: |
3.C. Amend Caselle Master Agreement
|
||
|
Discussion:
City Administrator, Tom Ourada, discussed how the City is going cloud-based on Caselle. City Attorney, Anna Burge, added that it is just a generic service agreement, but since the City is changing the system and Caselle is hosting, they need the City to sign a new agreement.
|
|||
|
Action(s):
|
|||
|
Attachments:
|
|||
| Subject: |
3.D. Consider the Contractor's Pay Estimate No 3 Application for Payment From JEO Consulting Group, Inc for NLC, LLC for the 2024 Crete Street and Alley Improvements Engineer's Project No: 240578.00 in the amount of $474,008.61
|
||
|
Discussion:
City Administrator, Tom Ourada, discussed that they are the ones who have done the alley work, a fair amount of paving, and the water lines work.
|
|||
|
Attachments:
|
|||
| Subject: |
3.E. Discuss online payments with Caselle
|
||
|
Discussion:
City Administrator, Tom Ourada, discussed how the City now has an option to take payments through Caselle. Right now, it is $0.74 per transaction and between 1.5 and 2.5 percent per transaction for online bill paying. The City is currently paying for the fees, which is about $60 to $70 thousand a year. Now the City can pass that to the customer and make it a customer obligation. Through Caselle, customers who pay with cash or check will have no fee. ACH payments will be $0.74, and debit and credit cards will be 3 percent to pay online. No decision was made, as there was more discussion.
|
|||
|
Action(s):
|
|||
| Subject: |
4. Officers' Reports
|
||
|
Rationale:
|
|||
| Subject: |
5. Adjournment
|
||