July 14, 2020 at 9:00 AM - Buildings and Grounds Committee Meeting
| Minutes |
|---|
|
1. New Business
|
|
1.A. Architect's Supplemental Instructions (ASI) - 9
|
|
1.B. Architect's Supplemental Instructions (ASI) -10
Discussion:
Clarifies the dimensions of a concrete wall in the elevator shaft at the Elementary School.
|
|
1.C. Architect's Supplemental Instructions (ASI) -11
Discussion:
Change the fire rating in the science classrooms.
|
|
1.D. Proposal Request (PR) - 10
Discussion:
Was able to use masonry lintel instead of steel headers in 20 locations throughout HS and Elementary.
|
|
1.E. Proposal Request (PR) - 13
Discussion:
Changed accessories in the new locker room bathrooms (e.g., sink, grab bars, urinals).
|
|
2. Old Business
|
|
2.A. Proposal Request (PR) - 5
|
|
2.B. Proposal Request (PR) - 6
Discussion:
Change order was originally priced at $78,872. The amount will drop to $66,888 after further clarification on of pipe size to be used.
|
|
2.C. Proposal Request (PR) - 12
Discussion:
Eliminates electrical floor boxes in some science classrooms. Flooring changes in the special education classrooms.
|
|
2.D. Fence quotes for east elementary playground / parking lots · |
|
2.E. 4’x8’ turf mats for ES student drop off path and employee entry path (17) at north (12) at east
Discussion:
Each 4'x8' mat costs $210. The total cost will be a little over $6,000.
|
|
3. Construction Schedule
Discussion:
|