October 19, 2010 at 5:00 PM - Special
| Minutes |
|---|
|
1. CALL TO ORDER
|
|
1.A. PLEDGE OF ALLEGIANCE
|
|
1.B. ROLL CALL
|
|
2. ADOPTION OF AGENDA, ACTION ITEM
|
|
3. PUBLIC INPUT, INFORMATIONAL ITEM
Description:
This time is set aside for the public to make comments on items within the authority of this Board & are not for Board interaction at this time. Matters raised cannot be deliberated or acted upon until properly placed on a future agenda. A "request to speak" card must be completed & submitted to the Board President. A time limit of 3 minutes per person or 5 minutes for the spokesperson for a group may be imposed. Ten copies of handouts must be provided. Comments that are irrelevant, repetitious, slanderous, offensive, inflammatory, willfully disruptive or deemed personal attacks will not be permitted.
|
|
4. EXECUTIVE (CLOSED) SESSION OR NON-PUBLIC CONSULTATION WITH LEGAL COUNSEL
Description:
If necessary, the Board may recess for a closed Executive session or for a consultation with its legal counsel pursuant to NRS 241.015.2(b)(2) regarding potential or existing litigation.
|
|
5. RULING ON B&H CONSTRUCTION BID PROTEST, ACTION ITEM
Presenter:
Cameron McRae, Transportation/Maintenance & Operations Supervisor
Description:
Recommended Action: Decision on the bid protest filed by B&H Construction, Inc. dated 10/12/10 objecting to any award of the contract for the Pahrump Valley High School project to any company other than B&H Construction, Inc.
|
|
6. RULING ON MARTIN-HARRIS CONSTRUCTION BID PROTEST, ACTION ITEM
Presenter:
Cameron McRae, Transportation/Maintenance & Operations Supervisor
Description:
Recommended Action: Decision on the bid protest filed by Martin-Harris Construction dated 10/12/10 objecting to any award of the contract for the Pahrump Valley High School project to B&H Construction, Inc.
|
|
7. REJECTION OF BIDS AND/OR AWARD OF CONTRACT, ACTION ITEM
Presenter:
Cameron McRae, Transportation/Maintenance & Operations Supervisor
Description:
Recommended Action: That the Board rejects any bids that are non-responsive or from contractors determined by the Board to be non-qualified or not responsible for this project. The board then either determines it is in the public interest to reject all bids, or to award the contract for the Pahrump Valley High School project to the contractor submitting the "best bid" as defined in NRS 338.147.
|
|