March 19, 2013 at 6:30 PM - Business Committee Regular School Board Meeting
Agenda |
---|
1. Financial Report
|
1.A. Financial Report
Attachments:
(
)
|
1.B. Approval of Payment of Claims
This item is attached as an "extra" on board book. |
1.C. Budget Revisions
Attachments:
(
)
|
1.D. Wire Transfers
Attachments:
(
)
|
1.E. Investment Transactions
Attachments:
(
)
|
1.F. WADM Projections
Attachments:
(
)
|
1.G. Fund Raisers
Attachments:
(
)
|
1.H. Investments in School Children
Attachments:
(
)
|
2. Bids, R.F.P.s and Quotes Reports
|
2.A. Bids
|
2.A.1) PLACEHOLDER - for Bids Related to the LRFP
|
2.B. R.F.P.s
|
2.C. Quotes
|
2.C.1) Quote #4140 – 2013 Lawn Care Services
Quotes were solicited from six contractors for the annual 2013 District-wide Lawn Care Services. Three quotes were received in response to this request covering the period from April 28, 2013 through September 21, 2013 (21 weeks). The low quotes are based on site-specific quotes as follows: General Cleaning $13,629.00, Nick Stokes $8,965.95, Quality Lawn Care $42,567.00.
Description:
Recommendation: It is recommended the School Board approve the quotes as submitted above to complete the work defined in Quote #4140 – 2013 District-wide Lawn Care Services, for a total estimated annual (based on an estimated 21 weeks) amount of $65,161.95, with the option to extend 2013 services beyond September 21, 2013, depending on the growing season. It is further recommended that the Duluth School Board approve the two (2) additional contract extension options through September 2015, if the amount is determined acceptable by the Director of Business Services and the Property and Risk Manager.
Attachments:
(
)
|
2.C.2) PLACEHOLDER - for Quotes Related to the LRFP
|
3. Policies and Regulations
|
3.A. Policies
|
3.A.1) Bylaw 9095 - Order of Business for Regular Meetings
Attached is Bylaw 9095 - Order of Business for Regular Meetings with a proposed addition for monthly Recognition of students and staff.
Description:
Recommendation: It is recommended that the Duluth School Board approve the second reading of Bylaw 9095 - Order of Business for Regular Meetings.
Attachments:
(
)
|
3.B. Regulations
|
4. Contracts, Change Orders, and Leases
|
4.A. Contracts
|
4.B. Change Orders
|
4.B.1) Congdon Park Elementary School
Congdon Park ES LRFP – Structural Steel – Supply Change Order #4, Bid #1222, WS #4 – Ben’s Structural Fabrication, Inc. Change Order decrease to credit a missing J7 joist for the roof construction Deduct: $150.00 b. Congdon Park ES LRFP – Concrete Change Order #4, Bid #1222, WS #3 – Kelleher Construction, Inc. Change Order increase for concrete topping and vapor barrier at room #124 and concrete slab recess for the floor mat near door #132A Add: $3,468.00
Description:
Recommendation: It is recommended the School Board approve the change order as listed above at Congdon Park Elementary School reflecting a total increase of $3,318.00
Attachments:
(
)
|
4.B.2) Lincoln Park Middle School
a. Lincoln Park MS LRFP – Electrical, Communications and Security Change Order #15, Bid #1184, WS #37 – APi Electric Company Change Order increase to upgrade a cable for the paging system, modify the science classroom rough-ins, add floor box connections to the auditorium, and add shunt trip connections for the kitchen Add: $10,042.00 b. Lincoln Park MS LRFP – Electrical, Communications and Security Change Order #16, Bid #1184, WS #37 – APi Electric Company Change Order decrease to backcharge replacement parts for flush valves and faucets due to incorrect wiring Deduct: $2,581.00 c. Lincoln Park MS LRFP – Steel Erection Change Order #12, Bid #1184, WS #7 – Northern Industrial Erectors, Inc. Change Order increase to install seven type A railings at the auditorium handicap seating areas, deduct the stair G center railing, provide expansion anchors rather than the concrete slab to support the angle at stair A, and add a continuous 10” plate to stair F Add: $3,712.00 d. Lincoln Park MS LRFP – Tile Work Change Order #5, Bid #1184, WS #18 – Grazzini Brothers & Company Change Order increase to add CT-4 to full height at wash sinks outside 10 rooms Add: $7,433.00
Description:
Recommendation: It is recommended the School Board approve the change orders as listed above at Lincoln Park Middle School reflecting a total increase of $11,145.00.
Attachments:
(
)
|
4.B.3) Ordean East Middle School
a. Ordean East MS LRFP – Finish Hardware, HM Frames, Wood Doors - Supply Change Order #15, Bid #1165, WS #13 – Northern Door & Hardware, Inc. Change Order increase to provide wall magnets due to door hold open modifications and provide double pole/double throw door position switches due to door security system revisions Add: $2,567.00 b. Ordean East MS LRFP – Acoustical Ceilings Change Order #21, Bid #1165, WS #18 – W.A. Schaefer & Son Contracting, Inc. Change Order increase to install break metal so the smart board projector can be raised higher into the ceiling Add $ 224.00 c. Ordean East MS LRFP – Excavation/Site Earthwork Change Order #15, Bid #1165, WS #31 – Arnt Construction Company, Inc. Change Order decrease to credit for soil corrections at the chiller Deduct: $11,622.00
Description:
Recommendation: It is recommended the School Board approve the change orders as listed above at Ordean East Middle School reflecting a total decrease of $8,831.00.
Attachments:
(
)
|
4.B.4) PLACEHOLDER - for Change Orders Related to the LRFP
|
4.C. Leases
|
5. Resolutions
|
5.A. PLACEHOLDER – Resolution of Support for the Mini-master Plan for Duluth’s Memorial Park near Laura MacArthur School
|
5.B. Resolution B-3-13-3079- Designation of Depository and Acceptance of Collateral
Description:
Recommendation: It is recommended that the Duluth School Board approve Resolution B-3-13-3079- Designation of Depository and Acceptance of Collateral.
Attachments:
(
)
|
5.C. PLACEHOLDER – Resolution authorizing the purchase of properties relating to the Long-range Facilities Plan and relocation expenses that apply to these properties
|
5.D. PLACEHOLDER – Resolution authorizing the sale of properties relating to the Long-range Facilities Plan and relocation expenses that apply to these properties
|
5.E. PLACEHOLDER – Resolutions for Schematic Designs and Working Drawings related to the LRFP
|
6. Informational - These items are provided for informational purposes only an no action is required.
|
6.A. Expenditure Contracts
Superintendent Gronseth or the Director of Business and Finance has signed the following contracts during the month of February 2013
Attachments:
(
)
|
6.B. Revenue Contracts - None
|
6.C. Other Contracts - None
|
6.D. Facilities Management & Capital Project Status Report
Kerry Leider will be present to answer questions regarding the attached report.
Attachments:
(
)
|
6.E. Johnson Controls, Inc. Long-Range Facilities Plan Status Report
Kerry Leider will be present to answer questions regarding the attached report.
Attachments:
(
)
|
6.F. Change Orders Pertaining to the Long-range Facilities Plan
Kerry Leider will be present to answer questions regarding the attached report.
Attachments:
(
)
|
6.G. Contracts Pertaining to the Long-range Facilities Plan - None
|
6.H. Actuarial Presentation
A representative from Van Iwaarden was present to review the Actuarial Valuation of OPEB included with the report. |
6.I. Congdon Park Elementary School Retaining Wall
Adminstration presented information regarding the bids received to construct a retaining wall at Congdon Park Elementary School |
7. Future Items
|
7.A. Resolution of Support for the Mini-master Plan for Gary New Duluth Park near Stowe School
|
7.B. Workers’ Compensation and Property Liability Insurance Policies and Premium Designation
|