1. 2006 and 2008 BOND PROGRAM and LOCAL CONSTRUCTION PROJECT
|
|
1.A. Mission High School (MHS) and veterans Memorial High School (VMHS) Scoreboard Installation Project – Rick Hinojosa Structural Engineering
|
|
1.A.1. Status Report
|
|
1.A.2. Consideration and Approval for Final Completion for the MHS and VMHS Scoreboard Installation Project
Attachments:
()
|
|
1.B. Fire/Security Alarm & Intercom System for Mission Junior High School (MJHS) Project – PBK Architects
|
|
1.B.1. Status Report
|
|
1.B.2. Consideration and Approval for Substantial Completion for the Fire/Security Alarm & Intercom System for MJHS Project
Attachments:
()
|
|
1.C. MJHS Building Chiller Project – Halff Associates
|
|
1.C.1. Status Report
|
|
1.C.2. Consideration and Approval of Construction Documents for the MJHS Science Building Chiller Project
Attachments:
()
|
|
1.D. MHS Phase III Renovation Project – PBK Architects
|
|
1.D.1. Status Report
|
|
1.D.2. Consideration and Approval of CPR#22R to Change Hardware Doors in Cafeteria Area for the MHS Phase III Renovation Project
Attachments:
()
|
|
1.D.3. Consideration and Approval of CPR#29 for Parapet Roof Repair, Removal of Grease Trap and Additional Sewer Line for the MHS Phase III Renovation Project
Attachments:
()
|
|
1.D.4. Consideration and Approval of CPR#32 for Unforeseen Structural Condition at the Band Hall for the MHS Phase III Renovation Project
Attachments:
()
|
|
1.D.5. Consideration and Approval of CPR#34 to Replace All Existing Windows at Buildings M & N for the MHS Phase III Renovation Project
Attachments:
()
|
|
1.D.6. Consideration and Approval of CPR#35 for Unforeseen Existing Roof Condition at Buildings M & N for the MHS Phase III Renovation Project
Attachments:
()
|
|
1.E. Tom Landry Stadium Renovations Project – Alvarado Architects & Associates, Inc
|
|
1.E.1. Status Report
|
|
1.F. School Marquees Project – Rick Hinojosa Structural Engineering – Mr. Roosevelt Rios
|
|
1.F.1. Status Report
|
|
1.G. MHS and VMHS Tennis Court Lights and Canopy Project – Chanin Engineering - Mr. Roosevelt Rios
|
|
1.G.1. Status Report
|
|
1.H. 2006 and 2008 Financial Update and Qualified School Construction Bond (QSCB) Financial Update
Attachments:
()
|
|
2. INFORMATIONAL
|
|
2.A. North Side Swimming Pool Project - Update
|
|
2.B. Facility Needs Assessment Walk-thru in February 2017
|
|