August 8, 2013 at 7:00 PM - Facilities Committee
| Agenda |
|---|
|
1. 2006 BOND PROGRAM
|
|
1.A. Veterans Memorial High School (VMHS) Ag Department Addition Project– PBK Architects
|
|
1.A.1. Status Report
|
|
1.A.2. Consideration and Approval of Change Order #2 for Forty Five (45) Additional Days Due to Modify and Reinstall Aluminum Canopies for the VMHS Ag Department Project
Attachments:
()
|
|
1.B. R. Cantu Junior High MEP Repairs – PBK Architects
|
|
1.B.1. Status Report
|
|
1.C. 2006 Financial Update
Attachments:
()
|
|
2. 2008 BOND PROGRAM
|
|
2.A. Waitz Elementary Kitchen Renovation Project – EGV Architects
|
|
2.A.1. Status Report
Attachments:
()
|
|
2.B. District Wide Roofing Projects- ERO International
|
|
2.B.1. Status Report
|
|
2.B.2. Consideration and Approval of Change Proposal Request #1 Replace Corroded “Z” Bar for the Cantu Elementary Re-Roofing Project
Attachments:
()
|
|
2.B.3. Consideration and Approval of Change Proposal Request #2 to Apply Roofing to Existing Canopies for the Cantu Elementary Re-Roofing Project
Attachments:
()
|
|
2.B.4. Consideration and Approval of Change Proposal Request #3 for Sixty-one (61) Additional Days for the District-Wide Re-Roofing Project (Bid Package #2)
Attachments:
()
|
|
2.B.5. Consideration and Approval of Change Proposal Request #4 for Sixteen (16) Additional Days for the District-Wide Re-Roofing Project (Bid Package #1)
Attachments:
()
|
|
2.C. Additional 2008 Bond Projects
|
|
2.C.1. Status Report
|
|
2.C.1.(a) Leal Elementary Ramp Enclosures – EGV Architects
Attachments:
()
|
|
2.C.1.(b) Ag Farm Master Plan Renovations – PBK Architects
|
|
2.C.1.(c) Ag Farm Driveway and Parking Renovations – Javier Hinojosa Civil Engineering
|
|
2.C.1.(d) Cantu Elementary Ramp Enclosures/HVAC – EGV Architects/ Halff Associates
Attachments:
()
|
|
2.C.1.(d)a) Consideration and Approval of Change Order #1 for Fire Extinguishers and Four (4) Additional Days for the Cantu Elementary Ramp Enclosures/HVAC
Attachments:
()
|
|
2.C.1.(d)b) Request to Halff Associates from SMAC for Additional Days
Attachments:
()
|
|
2.D. Mims/O’Grady Elementary Ramp Enclosures – PBK Architects
|
|
2.D.1. Status Report
|
|
2.D.2. Consideration and Approval Change Proposal Request #1 for Additional Concrete Work at the Door Landing for the Mims/O’Grady Elementary Ramp Enclosures
Attachments:
()
|
|
2.D.3. Consideration and Approval of Change Proposal Request #2 “Credit” for Door Hardware for the Mims/O’Grady Elementary Ramp Enclosures
Attachments:
()
|
|
2.D.4. Consideration and Approval of Change Proposal Request #3 Demolish/Pour New Concrete for the Mims/O’Grady Elementary Ramp Enclosures
Attachments:
()
|
|
2.E. Drainage Project at VMHS Courtyard – Javier Hinojosa Civil Engineering
|
|
2.E.1. Consideration and Approval of Substantial/Final Completion and Final Payment for the Drainage Project at VMHS Courtyard Drainage Project
Attachments:
()
|
|
2.E.2. Consideration and Approval of Change Order #2 "Credit" for Reconciliation of Quantities for the Drainage Project at VMHS Courtyard Drainage Project
Attachments:
()
|
|
2.F. Mission High School (MHS) Phase III Renovation - ERO International
|
|
2.F.1. Status Report
|
|
2.G. 2008 Financial Update
Attachments:
()
|
|
3. OTHERS
|
|
3.A. MHS Field House Project – EGV Architects
|
|
3.A.1. Status Report
Attachments:
()
|
|
3.A.2. Consideration and Approval of Change Order #1 for Eight (8) Additional Days for the MHS Field House Project
Attachments:
()
|
|
3.B. VMHS Field House Project – PBK Architects
|
|
3.B.1. Status Report
|
|
3.B.2. Consideration and Approval of Change Proposal Request #10, #11 and #18 for Relocate/Add TV’s, Relocate Electrical Conduit and Repair Electrical Equipment for the VMHS Field House Project
Attachments:
()
|
|
3.B.3. Consideration and Approval of Change Order #3 for one (1) Rain Delay Day in June and Five (5) Rain Delay Days in July for the VMHS Field House Project
Attachments:
()
|
|
3.B.4. Status on Payment for Supplies and Sub-Contractors
Attachments:
()
|
|
3.C. MHS Tom Landry Visitors Parking Lot, Leo Najo Baseball Parking Lot and M.H.S. Girls Softball Parking Lot- Javier Hinojosa Civil Engineering
|
|
3.C.1. Status Report
|
|
3.C.2. Consideration and Approval for Schematic Design for the MHS Girls Softball Parking Lot
Attachments:
()
|
|
3.C.3. Consideration and Approval for Schematic Design for the MHS Tom Landry Visitors Parking Lot, Leo Najo Baseball Parking Lot
Attachments:
()
|
|
3.D. Mission Collegiate High School – EGV Architects and Javier Hinojosa Civil Engineering
|
|
3.D.1. Status Report
|
|
3.E. Tom Landry Stadium Press Box Project –Rick Hinojosa Structural Engineering
|
|
3.E.1. Status Report
|
|
3.F. Child Nutrition Program (CNP) Addition – PBK Architects
|
|
3.G. Qualified School Construction Bond (QSCB) Financial Update
Attachments:
()
|