January 18, 2012 at 6:30 PM - Facilities Committee
| Agenda |
|---|
|
1. 2006 BOND PROGRAM
|
|
1.A. Marcell Elementary Chiller Replacement Status Report
|
|
1.B. Veterans Memorial High School Chiller Replacement Bid Tabulation and Ranking
|
|
1.C. Veterans Memorial High School Agriculture Department Addition Update
|
|
1.D. Approval to Enter Into Contract With Javier Hinojosa Civil Engineering for
the Veterans Memorial High School Agriculture Department Addition |
|
1.E. 2006 Financial Update – If Available
|
|
2. 2008 BOND PROGRAM
|
|
2.A. K. White Junior High Kitchen Renovation Bid Tabulation and Ranking
|
|
2.B. Waitz Elementary Kitchen Renovation Progress Report
|
|
2.B.1. Status Report – Presentation of Location Option
|
|
2.C. Veterans Memorial High School Science/Math Classroom Additions Progress Report
|
|
2.C.1. Status Report – Progress Timeline
|
|
2.D. Alton Elementary Renovations Progress Report
|
|
2.D.1. Status Report – Progress Timeline
|
|
2.E. District Wide Roofing Project Update
|
|
2.F. Leal Elementary School Drainage Update
|
|
2.F.1. Consideration of Procurement Method, Selection Criteria, Review and Ranking Committee, Wage Rate, and Authorization to Seek Proposals/Bids for the Leal Elementary Drainage Improvements
|
|
2.F.2. Approval to Enter into Contract with Javier Hinojosa Civil Engineering for Services for Drainage Needs at Leal Elementary
|
|
2.G. Veterans Memorial High School Drainage Update
|
|
2.G.1. Consideration of Procurement Method, Selection Criteria, Review and Ranking Committee, Wage Rate, and Authorization to Seek Proposals/Bids for the Veterans Memorial High School Drainage Improvements
|
|
2.G.2. Approval to Enter into Contract with Javier Hinojosa Civil Engineering for Services for Drainage Needs at Veterans Memorial High School
|
|
2.H. 2008 Financial Update – If Available
|
|
3. Others
|
|
3.A. Central Kitchen Boiler Consideration of Final Negotiated Proposal from
Hot Rod Mechanical |
|
3.B. Approval of Final Design & Development of Plans and Specifications for the
Veterans Memorial High School Field House |
|
3.C. Consideration and Approval of Procurement Method, Selection Criteria, Review and Ranking Committee, Wage Rate, and Authorization to Seek Proposals for Proposed New Transportation Facility
|
|
3.D. Approval to Enter Into Contract with Javier Hinojosa Civil Engineering for Services for the Proposed New Transportation Facility
|
|
3.E. Status Report of Roofing at Lee Field House
|
|
3.E.1. Consideration of Procurement Method, Selection Criteria, Review and Ranking Committee, Wage Rate, and Authorization to Seek Proposals/Bids for the Roofing at Lee Field House
|
|
3.E.2. Approval to Enter into Contract with Rick Hinojosa Structural Engineer for Services for the Roofing at Lee Field House
|
|
3.F. Escobar/Rios Elementary School Sidewalk Construction
|
|
3.G. Roofing
|
|
3.G.1. Old Cafeteria Roof at Castro Elementary
|
|
3.G.1.(a) Consideration of Procurement Method, Selection Criteria, Review and Ranking Committee, Wage Rate, and Authorization to seek Proposals/BIds for the Roofing of the Old Cafeteria at Castro Elementary
|
|
3.G.1.(b) Approval to Enter into Contract with Rick Hinojosa Structural Engineer for Roofing Assessment of the Old Cafeteria at Castro Elementary
|
|
3.G.2. District Warehouse Roof
|
|
3.G.2.(a) Consideration of Procurement Method, Selection Criteria, Review and Ranking Committee, Wage Rate, and Authorization to seek Proposals/Bids for the Roofing at District Warehouse
|
|
3.G.2.(b) Approval to Enter into Contract with Rick Hinojosa Structural Engineer for Roofing Assessment of the District Warehouse
|