February 9, 2011 at 7:00 PM - Facilities Committee
| Agenda |
|---|
|
1. 2006 BOND PROGRAM
|
|
1.A. 2006 Financial Update
|
|
2. 2008 BOND PROGRAM
|
|
2.A. Alton Elementary Renovation Progress Report
|
|
2.A.1. Status Report
|
|
2.A.2. Change Proposals
|
|
2.A.2.(a) CPR #8 - Add Temporary Fencing at Administration Building
|
|
2.A.2.(b) CPR #13 - Credit for Paint on Salvaged Canopy
|
|
2.A.2.(c) CPR #14 - Change in Drawing C-5 Including all Plant, Labor and Materials
|
|
2.A.2.(d) CPR #15 - Changes to Existing Sewer Adjustments
|
|
2.A.2.(e) CPR #18R1 - Labor for Additional Concrete Ramps
|
|
2.A.2.(f) CPR #19 - Entrance Steel Canopy Changes
|
|
2.A.2.(g) CPR #21 - Credit for Canopy Materials
|
|
2.A.2.(h) CPR #24 - Modify Parapet Wall
|
|
2.A.2.(i) CPR #25 - Installation of ¼” Slope with Tapered Insulation
|
|
2.A.3. Security Issues
|
|
2.B. Leal Elementary Renovations Progress Report
|
|
2.B.1. Status Report
|
|
2.B.2. Security Issues
|
|
2.C. Mims Elementary Kitchen Renovation Progress Report
|
|
2.C.1. Status Report
|
|
2.C.2. Security Issues
|
|
2.D. O’Grady Elementary Kitchen Renovation Progress Report
|
|
2.D.1. Status Report
|
|
2.D.2. Security Issues
|
|
2.E. K. White Junior High Kitchen Renovation Progress Report
|
|
2.E.1. Status Report
|
|
2.E.2. Security Issues
|
|
2.F. Waitz Elementary Kitchen Renovation Progress Report
|
|
2.F.1. Status Report
|
|
2.F.2. Security Issues
|
|
2.G. Veterans Memorial High School Science/Math Classroom Additions Progress Report
|
|
2.G.1. Status Report
|
|
2.G.2. Consideration and Approval of Change Proposal #1 to Provide/Install FDC Extensions, Fabricate and Install Stairs/Handrails
|
|
2.G.3. Security Issues
|
|
2.H. 2008 Financial Update
|
|
3. OTHERS
|
|
3.A. Daktronics Scoreboard Update
|