October 18, 2005 at 6:30 PM - Facilities Committee
| Agenda |
|---|
|
1. For Board Action October 24, 2005
|
|
1.A. Selection of Competitive Sealed Proposals Contractor for Indian Springs Middle School and South Keller Intermediate School Additions
|
|
1.B. Change Order #1 - Off-Site Utility Improvements for New Middle School and Intermediate School Contract
|
|
2. Review
|
|
2.A. Maintenance and Operations List Schedule and Budget
|
|
2.B. Priority 1 Maintenance Projects Schedule and Budget
|
|
3. Discussion
|
|
3.A. Prototype and Methodology of Delivery for Elementary #19
|
|
3.B. Schedule for Keller Learning Center Addition
|
|
4. Information
|
|
4.A. RFP for Construction Manager at Risk - Keller High School Addition
|
|
4.B. Change Order No. 2 - Keller Hicks Road Improvements for New Middle School and Intermediate School Contract
|
|
4.C. Projected Timelines on Remaining 2005 Bond Projects
|
|
5. Schedule Next Meeting
|
|
6. Adjourn
|