July 30, 2026 at 7:30 AM - Projects Committee Meeting
| Agenda |
|---|
|
1. UNFINISHED BUSINESS
|
|
2. SWCP
|
|
2.A. SWCP Application Approvals
Rationale:
Attached is a list of NSWCP applications for FY 27 approval. Due to the loss of State funding a portion of the NSWCP program we have limited the approvals to cover crops and three structure applications. We already have one structure application approved for summer construction.
The estimated cost-share for FY27 is $86,725.01
Recommended Motion(s):
To approve highlighted applicants for FY27 NSWCP and allocate $86,725.01 Passed with a motion by Board Member #1 and a second by Board Member #2.
Attachments:
()
|
|
2.B. SWCP Payments
|
|
2.C. SWCP Cancellations
|
|
2.D. Wahoo Creek Cost Share Approvals
|
|
3. JOINT WATER MANAGEMENT ADVISORY BOARD (JWMAB)
|
|
3.A. East Fremont/Elkhorn Township Drainage - FEMA HMPG
|
|
3.B. West Fremont - FEMA BRIC
|
|
3.C. Rawhide Creek Watershed - NRCS WFPO
|
|
3.D. North Bend Drainage District
|
|
3.E. Cotterell Diking and Drainage District
|
|
4. SHELL CREEK WATERSHED
|
|
4.A. Shell Creek Implementation - 319 & NET
Rationale:
Gene Wissenburg, Matt Bailey, and Ryan Chapman joined 3 teachers and 8 students from Newman Grove and Schuyler schools at the SWCS international conference in St. Louis. Gene and Matt gave a great presentation on Monday just before lunch. They entertained lots of questions at the end of their presentation that even lingered into lunchtime. Students presented an oral presentation on Wednesday morning and were at their poster during designated times to answer questions and engage with conference goers. Their poster turned out great - a big thanks to Anni Poetzl (DWEE/UNL-Extension) for printing! Staff will get some more info and pictures out on socials in the coming days.
For the 2023 SWCS conference, we approved stipends of $130 per day for teacher chaperons. This was based on substitute teacher pay rates. Directors receive $65 per day and we have a history of using that rate for SCWIG members. Matt will run his through directors quarterly reimbursement. We also anticipate covering mileage for the schools utilizing appropriate federal rates. SCWIG has a meeting on August 7th, 10:00 am to hear from UNL and NRCS experts on GPS cattle collars. This is expected to be a cost-effective alternative to cross fencing and livestock exclusion fencing. A cost share recommendation is expected coming out of this meeting. On 7/20 Maslonka, Elliott, and Bill Bos met with representatives from the Village of Newman Grove to inspect a drainage concern in the golf course. The problem is at the south-east portion of the golf course there is a low spot that will back up and flood two holes on the course. There is an existing 24" CMP culvert that drains to Shell Creek, however, the outlet portion of the culvert is silted in significantly, and thus will not drain. The issue stems from the bridge over Shell Creek on HWY 45 to the east causing the creek to silt in upstream. We discussed multiple alternatives but the Village, and the golf course, are very limited in funds so scenarios involving cost-share BMPs are unlikely due to design scope. We will plan to discuss this further at our next SCWIG meeting on 8/7.
Recommended Motion(s):
Approve stipend for Ms. Pieke, Ms. Miller, and Mr. Miller of $520 each, approve stipend for Mr. Wissenburg of $260, and reimburse schools for milage at current federal rate. Passed with a motion by Board Member #1 and a second by Board Member #2.
|
|
5. WAHOO CREEK WATERSHED
|
|
5.A. Construction Update
Rationale:
Monthly construction update details:
TCI invoice attached
Attachments:
()
|
|
5.B. Dam Site Planning Update
|
|
5.B.1. Design - Olsson
Rationale:
Site 84 is done with the review process and is waiting for final approval from Tim Gokie, DWEE Dam Safety. Site 77 is currently under review and Olsson believes the review should go smoothly as 77 has already gone through Federal (NRCS) review.
ACOE is reviewing our 404 permit for remaining sites and have not had any negative comments so far. There was (another) Project Manager put in charge of our area and so there is the usual backlog as they are brought up to speed. We expect the permit within the month. Saunders County Board of Supervisors approved our floodplain/conditional use permits for sites 55, 84, & 77 at their 7/21 meeting. |
|
5.B.2. Real Estate - Olsson & Great Plains Appraisal
Rationale:
Updates on remaining acquisitions for sites 66 & 86.
|
|
5.B.3. Funding - NRCS WFPO & NeDNR JEDI
|
|
5.C. Water Quality - NWQI & 319
Rationale:
The Wahoo Creek Watershed 319 Project Implementation Plan was approved by EPA. We are awaiting DWEE signature to begin the project.
|
|
6. LOWER PLATTE RIVER CORRIDOR ALLIANCE
|
|
7. MORSE BLUFF FLOOD REDUCTION
Rationale:
Mainelli Wagner is in the process of getting the alignment finalized and full quantities ran. After they get this done, we will have a new/better construction estimate.
|
|
8. LESHARA DRAINAGE IMPROVEMENT
|
|
9. EROSION AND SEDIMENT RULES AND REGULATIONS
|
|
10. HAZARD MITIGATION PLAN UPDATE
|
|
11. OTHER
|
|
11.A. FY2027 Budget Review
|
|
12. ADJOURNMENT
|