October 6, 2020 at 9:00 AM - Buildings and Grounds Committee Meeting
| Agenda |
|---|
|
1. New Business
|
|
1.A. Proposal Requests
|
|
1.A.1) PR 21
Discussion:
Rejected and kept the roof access door.
|
|
1.B. Architectural Supplemental Instructions
|
|
1.C. Field Change Orders
|
|
2. Old Business
|
|
2.A. Proposal Requests
|
|
2.A.1) PR 19
Discussion:
We'll wait until spring 2021 to decide whether or not to move forward with new hallway lights and ceiling tiles in Area B at the HS.
|
|
2.A.2) PR 20
Discussion:
Waiting on estimated costs for installing a new fire pump required at the HS.
|
|
2.B. Field Change Orders
|
|
2.B.1) FCO 17
Discussion:
$8,612 added cost to set the HVAC on top of the roof at Area B. There was missing information between bid packages one and two.
|
|
2.B.2) FCO 19
Discussion:
A lot of floor patching in the science classrooms. They charged us only 25% extra to work over the Labor Day holiday weekend. Total cost is $5,527.
|
|
3. Construction Schedule
|
|
3.A. High School Remodel
Discussion:
Area B at HS
|
|
3.B. Elementary School Remodel
|
|
3.C. High School Addition
|
|
3.D. Elementary School Addition
Discussion:
|
|
4. Update on Punch List
|
|
5. Comments and Questions
|