June 23, 2020 at 9:00 AM - Buildings and Grounds Committee Meeting
| Agenda |
|---|
|
1. Approval of Agenda
|
|
2. New Business
|
|
2.A. Architect's Supplemental Instructions (ASI) 03 - BP 2 Architectural Plan Revisions
Description:
Issed on 6/22/2020
Discussion:
State wants a few changes to the plans.
|
|
2.B. Architect's Supplemental Instructions (ASI) 05 - Roof Deck Angle Splices
Description:
Issued on 6/16/2020
Discussion:
State wants a few changes made to the plans.
|
|
2.C. Field Change Orders (FCO) for Changes to Science Classroom Plumbing
Discussion:
Plumbers found some of the existing piping in the science classrooms are not up to code. These will need to be updated when attached to the new piping for the remodel.
|
|
2.D. Vacant Lot Available for Parent Pick-up/Drop-off
Discussion:
Don will look into costs for 4x8 mats. This vacant lot will be used by students as a pathway to parents picking-up and dropping them off for school.
Attachments:
()
|
|
3. Old Business
|
|
3.A. Proposal Request (PR) 05 - State Building Review Revisions
Description:
To be Issued
Discussion:
The state wants changes made to some of the interior signage in the building, doors, and door hardware.
|
|
3.B. Proposal Request (PR) 06 - State Plumbing Review Revisions
Description:
Issued on 6/12/2020
Discussion:
Size of storm piping inside the building needs to be enlarged.
|
|
3.C. Proposal Request (PR) 08 - Relocate Exterior Wall 20’ South to Enlarge Commons 170
Description:
Issued on 6/12/2020
Discussion:
Cost to extend the wall in the commons area is approximately $84,000.
|
|
3.D. Field Change Order (FCO) 02 - Parking Lot at East Side of ES
Discussion:
The parking lot will be completed later this week. Don will receive pricing on both temporary and permanent fencing.
|
|
3.E. Field Change Order (FCO) 03 - Remove City Well House and Cap Abandoned Well at New HS Pond
Discussion:
$856 change order for digging down and capping off the abandoned well.
|
|
4. Construction Schedule
Discussion:
All footings are dug for the Elementary School addition.
In the science classrooms the door frames will be arriving in two (2) weeks and structural steel on Monday, June 29. |