July 25, 2024 at 9:00 AM - Regular Meeting
Agenda |
---|
1. CALL TO ORDER/QUORUM
|
2. PLEDGE OF ALLEGIANCE
|
3. INVOCATION
|
4. PUBLIC COMMENTS
|
5. MEETING MINUTES
|
6. APPROVAL OF TRAVEL
|
7. FINANCIAL REPORT
|
7.A. DISBURSEMENTS
|
7.B. LICENSES
|
7.C. PROGRESS PAYMENTS
|
7.C.1. BALCH & BINGHAM, LLP / 18-FD-04
FILL PERMIT CHALLENGE - $ 5,652.37 GENERAL LEGAL SERVICES - $ 1,292.50 YILPORT LITIGATION - $ 2,698.00 TOTAL BALCH & BINGHAM - $ 9,642.87 |
7.C.2. DREDGING PROFESSOR, LLC / 23-EN-03
DEEPENING & WIDENING CONSULTING - $ 480.00 |
7.C.3. GULF REGIONAL PLANNING COMMISSION - STP-0200-00(34)LPA/108814-711000
TRAFFIC SIGNAL COORDINATION STUDY - $ 8,649.63 |
7.C.4. HDR ENGINEERING, INC. / 24-EN-04
CLEAN PORTS ZERO EMISSION GRANT APP. - WORK ORDER 2 - $ 23,535.00 CLEAN PORTS PLANNING GRANT APP. - WORK ORDER 3 - $ 13,500.25 TOTAL HDR ENGINEERING - $ 37,035.25 |
7.C.5. MP DESIGN GROUP / 22-EN-02
ACCESS ROAD PROJECT (MARAD) - $ 1,964.73 |
7.C.6. MP DESIGN GROUP / 23-EN-01
GENERAL ENGINEERING - WORK ORDER 1 - $ 7,422.00 PAVING - TRAILER LANDING GEAR - WORK ORDER 3 - $ 2,845.00 USM/NOAA PIERS (GCRF) - WORK ORDER 4 - $ 18,777.58 ASSET MGMT/INSPECTION PROGRAM - WORK ORDER 6 - $ 1,545.50 SHED 50 FIRE PROTECTION & REPAIRS - WORK ORDER 9 - $ 9,783.65 BASIN HYDROGRAPHIC SURVEY - WORK ORDER 10 - $ 18,718.01 TOTAL MP DESIGN GROUP - $ 59,091.74 |
7.C.7. MICRO-METHODS LABORATORY
DEMOLITION 34th AVE PROPERTY- $ 2,750.00 |
7.C.8. SOUTHERN EARTH SCIENCES / 21-EN-04
TRAILER LANDING GEAR - $ 1,390.00 DRAIN INLET REPAIRS - $ 895.00 TOTAL SOUTHERN EARTH SCIENCES - $ 2,285.00 |
7.C.9. SPARKLIGHT
EAST PIER POWER LINES RELOCATION PROJECT - $ 18,156.35 |
7.C.10. VICE BROTHERS UNLIMITED, LLC / 24-EN-02
DEMOLITION 34th AVE PROPERTY - $ 69,400.92 |
7.C.11. WARREN PAVING, INC. / 22-EN-03
TRAILER LANDING GEAR - PHASE 3 - WORK ORDER 7 - $ 25,353.78 TRAILER LANDING GEAR - PHASE 2 - WORK ORDER 8 - $ 164,790.47 DRAIN INLET REPAIRS - WORK ORDER 9 - $ 90,569.20 TOTAL WARREN PAVING - $ 280,713.45 |
7.C.12. WSP USA, INC. / 24-EN-03
MARKET ANALYSIS FOR DREDGE PROJECT - WORK ORDER 3 - $ 723.19 PIDP GRANT APPLICATION - WORK ORDER 5 - $ 8,798.33 COMMUNITY ADVISORY COMMITTEE - WORK ORDER 6 - $ 4,975.95 EPA CLEAN PORTS GRANT APPLICATION - WORK ORDER 7 - $ 1,449.05 DREDGE CONTAINMENT STRUCTURES - WORK ORDER 8 - $ 4,994.33 INFRA GRANT APPLICATION - WORK ORDER 9 - $ 3,714.51 TOTAL WSP - $ 24,655.36 |
7.C.13. DNP, INC. / 24-EN-06
E PIER DEEP WATER WHARF USM/NOAA (GCRF) - $ 80,683.50 |
8. OLD BUSINESS
|
8.A. (JB) APPROVAL OF PROJECT CLOSEOUT AND NOTICE OF COMPLETION FOR CONTRACT 24-EN-02 DEMOLITION OF 2810 34TH AVE PROPERTY
Description:
This agenda item seeks Board approval to accept the work, close the contract, and issue a Notice of Completion for Vice Brothers Unlimited, LLC's contract 23EN02 Demolition of 2810 34th Avenue Property.
|
8.B. (JB) APPROVAL OF MODIFICATION AND CLOSEOUT OF ENGINEERING WORK ORDERS WITH WSP, INC UNDER CONTRACT NO. 24-EN-03:
MODIFICATION NO. 1 TO WORK ORDER NO. 5 - < $ 393.91> MODIFICATION NO. 1 TO WORK ORDER NO. 7 - < $ 16,836.11> MODIFICATION NO. 1 TO WORK ORDER NO. 9 - < $ 7,489.09>
Description:
This agenda item seeks approval of the following work order modifications with WSP, Inc under Contract No. 24-EN-03:
|
8.C. (JB) APPROVAL OF MODIFICATION AND CLOSEOUT OF ENGINEERING WORK ORDERS WITH HDR ENGINEERING, INC UNDER CONTRACT NO. 24-EN-04:
MODIFICATION NO. 1 TO WORK ORDER NO. 2 - < $ 253.25> MODIFICATION NO. 1 TO WORK ORDER NO. 3 - < $ 38,475.75>
Description:
This agenda item seeks approval of the following work order modifications with HDR Engineering, Inc under Contract No. 24-EN-04:
|
8.D. (DW) AUTHORIZATION TO NAME MSPA AGENTS FOR FEMA AND HURRICANE ZETA DISASTER ASSISTANCE
Description:
Staff requests approval to designate Shawn Meyer as the Applicant Agent for Public Assistance and Tammy Salisbury as Alternate Applicant Agent.
|
9. NEW BUSINESS
|
9.A. (DW) APPROVAL OF FY 2026 LBO BUDGET
Description:
The fiscal year 2026 LBO Budget, which covers the period of July 1, 2025 - June 30, 2026, is due to the State and Legislative Budget Office on August 1, 2024. The total budgeted expenditures, including capital projects, are $ 78,863,297.00. Staff recommends approval of the attached FY 2026 LBO Budget, as presented.
|
10. ENGINEERING UPDATE
|
11. OPERATIONS REPORT
|
12. EXECUTIVE DIRECTOR'S REPORT
|
13. GENERAL COUNSEL'S REPORT
|
14. MDA COMMENTS
|
15. COMMISSIONERS' COMMENTS
|
16. EXECUTIVE SESSION - LEASE NEGOTIATION/PERSONNEL
|