January 26, 2023 at 9:00 AM - Regular Meeting
Agenda |
---|
1. CALL TO ORDER/QUORUM
|
2. PLEDGE OF ALLEGIANCE
|
3. INVOCATION
|
4. PUBLIC COMMENTS
|
5. MEETING MINUTES
|
6. APPROVAL OF TRAVEL
|
7. FINANCIAL REPORT
|
7.A. DISBURSEMENTS
|
7.B. LICENSES
|
7.C. PROGRESS PAYMENTS
|
7.C.1. ANDERCORP, LLC / 22-EN-05
SHED 53 - OCEAN AERO IMPROVEMENTS - $ 306,761.52 |
7.C.2. BALCH & BINGHAM, LLP / 18-FD-04
FILL PERMIT CHALLENGE - $ 470.00 GENERAL LEGAL SERVICES - $ 43,240.00 WHARTON SMITH - $ 1,351.25 YILPORT LITIGATION - $ 50,332.95 TOTAL BALCH & BINGHAM - $ 95,394.20 |
7.C.3. BENECORP, INC. / 22-EN-06
SHED 50 ROLL-UP DOORS (FEMA) - $ 180,612.48 |
7.C.4. DIGITAL ENGINEERING / 17-EN-04
EAST PIER ROAD IMPROVEMENTS - TASK 9 - $ 1,735.50 HURR ZETA SHED 50 ROLL-UP DOORS - TASK 14 - $ 13,158.00 HURR ZETA STONE/EROSION REPAIRS - TASK 20 - $ 19,781.50 HURR ZETA SHED 50 REPAIRS - TASK 21 - $ 4,231.00 10 YR MAINTENANCE DREDGING PERMIT - TASK 24 - $ 1,477.25 EAST PIER RAIL REPAIRS - TASK 25 - $ 5,486.50 TOTAL DIGITAL ENGINEERING - $ 45,869.75 |
7.C.5. MP DESIGN GROUP / 22-EN-02
ACCESS ROAD PROJECT (MARAD) - $ 22,714.98 |
7.C.6. MP DESIGN GROUP / 23-EN-01
GENERAL ENGINEERING - WORK ORDER 1 - $ 16,747.50 REEFER PLUG ELEVATION (FEMA) - WO #2 - $ 25,967.50 PAVING - TRAILER LANDING GEAR - WO #3 - $ 9,710.00 TOTAL MP DESIGN GROUP - $ 52,425.00 |
7.C.7. WSP / 22-EN-04
STRATEGIC MASTER PLAN - $ 64,613.25 |
7.D. REQUESTS FOR CASH
|
7.D.1. RESTORATION AGREEMENT RFC #339
CH2M HILL - $ 16,741.19 ELEY GUILD HARDY - $ 34,778.50 WHARTON SMITH - $ 171,963.99 TOTAL RFC #339 - $ 223,483.68 AS "OTHER FUNDING" SOURCE - MSPA |
8. OLD BUSINESS
|
8.A. (JB) APPROVAL OF CHANGE ORDER NO. 1 WITH ANDERCORP, LLC UNDER CONTRACT NO. 22-EN-05
Description:
This agenda item seeks Board approval of proposed Change Order No. 1 to the contract 22-EN-05 with AnderCorp, LLC for the Ocean Aero Shed 53 Renovations. Change Order No. 1 is a cumulation of AnderCorp's change order requests (CORs) #1 thru #7. These CORs were requested by the Lessee/User Ocean Aero. The total cost Change Order is an increase to contract in the amount of $17,984.27. No changes were requested to the contract days. Staff recommends that Change Order No. 1 to contract 22-EN-05 be approved as submitted.
|
8.B. (JB) APPROVAL OF THE FOLLOWING AMENDMENTS WITH ELEY GUILD HARDY UNDER CONTRACT 16-HUD-031:
AMENDMENT 3 TO TASK ORDER 9 - CONSTRUCTION ADMIN AMENDMENT 8 - CONSTRUCTION ADMIN
Description:
Both items seek approval to modify the Eley Guild Hardy Architects contract and task order schedule by adding 120 days to each, allowing continuation of Construction Administration services. Amendment 3 to Task Order 9 and Amendment 8 revise the expiration dates to April 30, 2023, with no changes to the scope of work. Staff recommends approval of both Amendment 3 to Task Order 9, and Amendment 8 to EGH contract 16-HUD-031 as presented.
|
9. ENGINEERING UPDATE
|
10. OPERATIONS REPORT
|
11. EXECUTIVE DIRECTOR'S REPORT
|
12. GENERAL COUNSEL'S REPORT
|
13. MDA COMMENTS
|
14. COMMISSIONERS' COMMENTS
|
15. PRESENTATION OF STRATEGIC MASTER PLAN - BLAIR GARCIA, WSP, INC.
|
16. EXECUTIVE SESSION - LEGAL MATTERS
|